九桥高尔夫俱乐部的凉棚是建立在对一棵古老的神树表示敬意的位置上的结构。在现在的高尔夫球场建成之前,这棵中国黑莓已经存在了大约600年,它无意识地灌输了一个万物有灵的地方。凉棚按照老树的方向重新安排场地,并在自然算法中找到其项目主题。

The Pergola of The Golf Club at NINE BRIDGES is a structure built on a location that honors an old sacred tree. The Chinese hackberry, which stood for roughly 600 years before the present golf course was constructed, unconsciously instated a place of animism. The pergola rearranges the site in accordance with the orientation of an aged tree and finds its project motifs in natural algorithms.

受自然算法的基本结构的启发,我们设计了一个 “双管道系统”,将结构和设施结合起来。内部管道用于通风,用12毫米厚的钢架包裹,形成整体结构。两个风道之间覆盖着高度密集的绝缘材料,以防止在运行制冷和加热系统时室内外温差造成的结露。

Inspired by the essential structures of natural algorithms, we have devised a ‘dual-duct system’ that integrates both the structure and the facility. The inner duct is used for ventilation and wrapped with a 12mm thick steel frame to form the overall structure. The two ducts are covered with highly dense insulating material in between, to prevent dew condensation from indoor-outdoor temperature difference when operating cooling and heating systems.

为了控制这种用双曲面完成的有机形式,使用了6个主结构和19个子结构。大约160块非典型的半钢化玻璃被放置在结构上,大约280块弧形玻璃被放置在侧翼。440块不同大小的玻璃板是在中国的一家工厂生产的,并组装在当地生产的结构上。在首尔附近的一家工厂生产的内部结构被拆成80块,运到济州岛重新组装。半钢化成对的玻璃板,有140种不同的弧度,在中国的工厂生产,在韩国组装。

To control this organic form finished with double curved surfaces, 6 main structures and 19 substructures were used. About 160 atypical, semi-tempered pair panes of glasses were placed on the structure and roughly 280 curved panes of glasses were applied on the flank. 440 glass panes of differing sizes were manufactured in a factory in China and assembled onto a locally manufactured structure. The inner structure produced at a factory near Seoul was disassembled into 80 pieces and shipped to Jeju Island for reassembly. The semi-tempered paired glass panes, with 140 different curvatures, were manufactured at the Chinese factory and assembled in Korea.

这是一项需要精密的工作,只允许在韩国和中国分别制造的材料在现场重新组装时有不到5毫米的差异。该结构主要分为六股,安装了48根通风管,以应对外部空气温度并保持室内温度的稳定。

This was a task that required sophistication, only allowing for a less than 5mm difference between the materials manufactured separately in Korea and China when they were to be reassembled at the site. The structure was mainly divided into six strands had a ventilation duct installed with 48 duct pipes to respond to the outside air temperature and to maintain a consistent indoor temperature.

Architects: JOHO ArchitectureArea : 264 m²
Year : 2016
Photographs :Archframe
Manufacturers : IlJIN Unisco, Jeju Basalt
Construction : CJ Engineering & Construction, Iljin Unisco
Design Team : Junhee Cho, Bong-gwi Hong, Moonyoung Jeong
City : Seogwipo-si
Country : South Korea